Build 11 – November Update

No 11 Assembly 2D Side

Progress on No. 11 continues, with fund raising for this year getting close to the goal. As of Nov. 9, it’s less than $1,000 from that $17,000 goal. Thanks to all the great folks who have contributed. We’re currently working on plans for a new fund raising project, to debut in January 2021, to help move the Build 11 Project forward for another year.

We can also report that we have received two competitive quotations for the major castings, and we expect to receive others as the Dec. 1 deadline approaches. The award will be made on that date, and as soon as all the documents are accepted and approved by both parties, that work will move forward.

Through no fault of our own, several patterns for No. 11, including the driver centers and cranks, were seriously damaged by water. As a result, they must be dried out and repaired before they can be used. Several of the core boxes are beyond repair, so new ones must be made. Since we won’t need these components right away, however, there is time to do what must be done.

As part of the Build 11 Project, several improvements to the shop are underway. The 20-inch Prentice lathe was recently sold and moved out, the the big New Haven lathe will soon follow it out the door. A 30-inch lathe has been acquired to handle the work formerly done by the two lathes, thereby gaining much-needed floor space in the shop. The new radial drill press is almost ready for use, and several machines are being relocated.

As the winter weather comes on, work in the heated shop will pick up. Flanging of the final components for No. 10’s boiler will be accomplished by the end of the year, and then work to flange boiler components for No. 11 can begin. If there are no major holdups, the flanging work for both boilers should be completed by spring.